Project Update

LakeCoal Pty Ltd (LakeCoal) received approval on the 23 January 2012 from the NSW Department of Planning and Infrastructure for the Chain Valley Colliery Domains 1 and 2 Continuation Project, under the Environmental Planning and Assessment Act, 1979. This approval allows the continuation of mining at Chain Valley until the 31st December 2016.

A Stakeholder Reference Group (SRG) meeting was held on Thursday 9 February to discuss the ongoing community consultation process.

A new Community Consultative Committee (CCC) will be established in accordance with the conditions of approval.  (See article below regarding applying for membership of the CCC and a proforma for nominations)

To view the assessment report and project approval documents, visit the Department of Planning and Infrastructure website here,  http://majorprojects.planning.nsw.gov.au/index.pl?action=view_job&job_id=4244

 

read more

The following links reload the page with different content below.

Project Application Update

Following adequacy review of the Chain Valley Mine Part B Continuation of Mining, Preliminary Environmental Assessment, the Department of Planning require further information prior to the EA going to Public Exhibition.

The studies will be completed in the New Year and it is expected the EA will be on Public Exhibition in late February 2011. A Stakeholder Reference Group meeting will be scheduled prior to this date.

The Department of Planning have taken action to extend the transitional period during which existing mines are exempt from requiring a major project approval under Part 3A of the Environmental Planning & Assessment Act 1979 till 31 December 2011, providing that the Department's Director – General has (on or before 16 December 2010) notified environmental assessment requirements under the Act.

The full text of the amendment is available at: http://www.legislation.nsw.gov.au/maintop/view/force/subordleg+557+2000+cd+0+N

Proforma for nomination to CCC

RE: CHAIN VALLEY COLLIERY – COMMUNITY CONSULTATIVE COMMITTEE

I would like to nominate _______________________________, as a potential representative for the Chain Valley Colliery Community Consultative Committee.

I understand the appointment for members is undertaken by the Director-General of the NSW Department of Planning and Infrastructure, which is based upon selection criteria in the Guidelines for Establishing and Operating Community Consultative Committees for Mining Project, June 2007 (the Guidelines).

I note the selection criteria for community and other stakeholders below and provide information for consideration of this nomination as detailed in points 1 to 3.

  1. Willingness to contribute constructively.

 

 

 

 

 

2Experience and ability to provide feedback to the community and stakeholder groups.

 

 

 

 

 

3Current residence in the local area and/or awareness of the local and other relevant issues.

 

 

 

 

 

The contact details for the person nominated above are:

Name:

 

Address:

 

Phone   Number:

 

Email   Address:

 

 

Other comments in relation to this nomination.

 

 

 

 

 

 

 

 

 

New Community Consultative Committee (CCC)

Call for Expressions-of-Interest for membership of Chain Valley Colliery

Community Consultative Committee (CCC)

 

In accordance with the conditions of approval for Chain Valley Colliery, a Community Consultative Committee (CCC) is to be established. 

The purpose of the CCC is to provide a forum for open discussion between representatives of the company, the community, the local council and other stakeholders on issues relating to the mine’s operations and environmental performance, and to keep the community informed of these matters.

LakeCoal are now seeking expressions-of-interest from community representatives, which will be forwarded to the Director-General of the Department of Planning and Infrastructure for selection and appointment to the committee.

Selection criteria for membership will include:

  • Willingness to contribute constructively;
  • Experience and ability to provide feedback to the community and stakeholder groups; and
  • Current residence in the local area and awareness of local issues.

It is expected that the CCC would meet approximately twice per year, or more frequently if required.

If you would like to nominate as a potential representative of the CCC please contact Chris Ellis on 0429774246 or cellis@ldo.com.au to obtain further information.

 

 

LakeCoal establishes levy to assist local community

LakeCoal has made a commitment to assist the local community, by paying a levy on each tonne of coal produced at the Chain Valley Mine. The levy will form part of the Part 3a (Part B) development application.

Two cents per tonne produced will go directly to Wyong Shire Council which will prioritise the funds for the benefit of the Summerland Point, Gwandalan, Chain Valley and Mannering Park communities.

An additional one and a half cents per tonne produced will go into the ‘Chain Valley Community Fund’. Although details of the Fund need to be finalised, it is envisioned that a



read more

Changes to Chain Valley Coal Project Application

LakeCoal has received notification from the Department of Planning that its application for continuation of mining at Chain Valley mine will need to be processed as two separate application.

This will ensure the Department of Planning can be process part one (named Part B) of the application by 16 December 2010. It is a requirement that all Coal Mines operating under existing use agreements have contemporary environmental approvals in place by this date.

The Part B application includes a selected area of the lease, where there are current Subsidence Management Plan approvals and will ensure continuation of operations. It is expected Part



read more

Proposal

LakeCoal Pty Ltd (a wholly owned subsidiary of LDO Coal Pty Ltd) has submitted an application to consolidate and replace existing approvals for the Chain Valley Coal Mine, effectively securing employment for the operation’s 120 employees.

The application has been made under Part 3A of the Environmental Planning and Assessment Act 1979 and would extend the life of the mine by 21 years to 2030.

The Chain Valley Coal Project will enable the continuation of underground mining operations at the Chain Valley Mine within the area covered by existing mining leases. The planned mining areas are located in the Swansea-North Entrance Mine



read more

Location

Location

The Chain Valley Coal Project will enable the continuation of underground mining operations at the Chain Valley mine within the area covered by existing mining leases. The planned mining areas are located in the Swansea-North Entrance Mine Subsidence District. This includes parts of Gwandalan, Summerland Point and Chain Valley Bay. Mining will also occur under parts of Lake Macquarie.

From the early 1960s to 1997 much of the application area, including Gwandalan and Summerland Point, was mined beneath in the Wallarah Seam.

Participation

An Environmental Assessment of the possible impacts of the project will be prepared in accordance with specific requirements set down by the Director-General of the Department of Planning. Once issued, these requirements will be available on the Department’s website at http://majorprojects.planning.nsw.gov.au/page/project-sectors/mining--petroleum---extractive-industries/mining/?action=view_job&job_id=3387

It is anticipated that one of these requirements will be community consultation. Consultation with the community will ensure that all factors of importance to the community will be considered in the Environment Assessment.

Once the Environmental Assessment is completed it will be submitted to the Department of Planning and placed on exhibition for community comment. Submissions can be made to the Department of Planning during this period.

All submissions will be considered and the Department will prepare a report for determination of the application by the Minister for Planning under Part 3A of the Environmental Planning & Assessment Act.